परियोजना प्रबंधन में कुल लागत वक्र के संदर्भ में, न्यूनतम कुल लागत एक विशिष्ट अवधि पर प्राप्त होती है। इस अवधि को क्या कहा जाता है?
- 1प्रारंभ अवधि (Start duration)
- 2इष्टतम अवधि (Optimum duration)✓
- 3अनुमानित अवधि (Approximate duration)
- 4अंत अवधि (End duration)
सही उत्तर देखें
इष्टतम अवधि (Optimum duration)