Computer · Construction Planning and Management
In the PERT method, the expected time E(T) for an activity is given by the expression (where O = optimistic time, M = most likely time, P = pessimistic time):
- 1E(T) = (O + M + 4P) / 6
- 2E(T) = (4O + M + P) / 6
- 3E(T) = (O + 4M + P) / 6✓
- 4E(T) = (O + 6M + P) / 6
Correct answer
E(T) = (O + 4M + P) / 6
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Planning and Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Planning and Management