Computer · Construction Planning and Management
In the PERT (Programme Evaluation and Review Technique) method, the expected time E(T) for a project activity is calculated using the formula where: Testbook + 1 O = optimistic time M = most likely time P = pessimistic time
- 1E(T) = O + 6M + P6
- 2E(T) = 4O + M + P6
- 3E(T) = O + M + 4P6
- 4E(T) = O + 4M + P6✓
Correct answer
E(T) = O + 4M + P6
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Planning and Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Planning and Management