In project management, when attempting to crash a network to reduce project duration, which of the following statements accurately describes the process and its implications?
- 1Crashing a network requires lengthening non-critical path activities to improve overall project efficiency and reduce duration.
- 2Crashing is the process of eliminating non-critical activities to speed up project completion without affecting the project cost.
- 3Crashing a network involves shortening the duration of critical path activities by increasing their cost, with the goal of reducing the overall project duration.✓
- 4Crashing a network focuses on reassigning resources from non-critical to critical path activities to avoid additional costs while reducing project duration.
Correct answer
Crashing a network involves shortening the duration of critical path activities by increasing their cost, with the goal of reducing the overall project duration.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Planning and Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Planning and Management