Computer · Project Management
परियोजना नेटवर्क में अन्य गतिविधियों के पूरा होने के बाद ही की जाने वाली गतिविधियों को ______ कहा जाता है।
- 1समांतर गतिविधि (Parallel activity)
- 2पूर्ववर्ती गतिविधि (Predecessor activity)
- 3उत्तराधिकारी गतिविधि (Successor activity)✓
- 4क्रमिक गतिविधि (Serial activity)
सही उत्तर देखें
उत्तराधिकारी गतिविधि (Successor activity)