Slack of an event in PERT is ____________.
- 1Latest Allowable Time minus Early Expected Time✓
- 2Early Expected Time minus Latest Allowable Time
- 3Early Allowable Time minus Latest Expected Time
- 4Latest Expected Time minus Early Allowable Time
Correct answer
Latest Allowable Time minus Early Expected Time