Consider the following data for a project of 300 days duration. Budgeted cost of work scheduled (BCWS) = Rs. 200 Budgeted cost of work performed (BCWP) = Rs. 150 Actual cost of work performed (ACWP) = Rs. 190 The 'schedule variance' (SV) for the project is:
- 1(-)Rs. 50✓
- 2(+)Rs. 50
- 3(+)50 days
- 4(-)50 days
Correct answer
(-)Rs. 50