इष्टतम समय (O), निराशावादी समय (P) और सर्वाधिक संभावित समय (M) के संदर्भ में PERT गतिविधि का अपेक्षित समय (E) किस सूत्र द्वारा दिया जाता है?
- 1E = (O + 4M + P) / 6✓
- 2E = (O + 2M + P) / 6
- 3E = (O + 4M + P) / 3
- 4E = (O + 2M + P) / 3
सही उत्तर देखें
E = (O + 4M + P) / 6