Computer · Construction Management
In a CPM network, if activities P and R originate from nodes with earliest event occurrence times of 8 and 13 respectively, then the early start times of activities P and R are:
- 14 and 13, respectively
- 28 and 13, respectively✓
- 36 and 10, respectively
- 48 and 12, respectively
Correct answer
8 and 13, respectively