One of the main limitations of a bar chart (Gantt chart) in construction scheduling is its inability to represent:
- 1Start and finish dates of activities
- 2Duration of each construction activity
- 3Logical relationships and dependencies between activities✓
- 4Progress of individual activities
Correct answer
Logical relationships and dependencies between activities