The expected time (E) of a PERT activity in terms of optimistic time (O), pessimistic time (P), and most likely time (M) is given by which formula?
- 1E = (O + 4M + P) / 6✓
- 2E = (O + 2M + P) / 6
- 3E = (O + 4M + P) / 3
- 4E = (O + 2M + P) / 3
Correct answer
E = (O + 4M + P) / 6