Mathematics · Construction Management
The normal duration and normal cost of an activity are 25 days and Rs. 50,000 respectively. The activity crash duration is 22 days. If the cost slope of the activity is Rs. 1,500 per day, what is the direct activity cost after crashing it fully by 3 days?
- 1Rs. 45,500
- 2Rs. 47,500
- 3Rs. 51,500
- 4Rs. 54,500✓
Correct answer
Rs. 54,500