Calculate the duration of the critical path for a project given the following activities, their immediate predecessors, and durations: - Activity A (Predecessor: None, 3 days) - Activity B (Predecessor: A, 4 days) - Activity C (Predecessor: A, 5 days) - Activity D (Predecessor: A, 4 days) - Activity E (Predecessor: B, 2 days) - Activity F (Predecessor: D, 9 days) - Activity G (Predecessor: C, E, 6 days) - Activity H (Predecessor: F, G, 2 days)
- 1A-B-C-F-H (23 days)
- 2A-C-G-H (16 days)
- 3A-D-F-H (18 days)✓
- 4A-B-E-G-H (17 days)
Correct answer
A-D-F-H (18 days)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Construction Management