A scraper is to haul earth from a pit to a fill 0.4 km away. If it is working under average fixed-time conditions of 2.2 minutes, with an average haul speed of 7 km/h, and an operating factor of 0.8, the number of cycles which can effectively be performed per hour is nearly:
- 15.4✓
- 26.4
- 38.5
- 49.6
Correct answer
5.4