In PERT analysis, calculate the expected time (Te) in days for an activity if the optimistic time (To) = 4 days, most likely time (Tm) = 6 days, and pessimistic time (Tp) = 12 days.
- 15.33
- 26.67✓
- 37.40
- 48.50
Correct answer
6.67