Computer · Construction Management
परियोजना मूल्यांकन और समीक्षा तकनीक (PERT) को किस रूप में वर्गीकृत किया गया है?
- 1संसाधन-स्तरीकरण तकनीक (Resource-leveling technique)
- 2समय-स्वतंत्र तकनीक (Time-independent technique)
- 3घटना-उन्मुख तकनीक (Event-oriented technique)✓
- 4गतिविधि-उन्मुख तकनीक (Activity-oriented technique)
सही उत्तर देखें
घटना-उन्मुख तकनीक (Event-oriented technique)