Mathematics · Industrial Engineering
परियोजना प्रबंधन में एक PERT गतिविधि का अपेक्षित समय (te) किस सूत्र का उपयोग करके निकाला जाता है? [जहाँ to = आशावादी समय, tm = सर्वाधिक संभावित समय, tp = निराशावादी समय]
- 1to + 4tp + tm6
- 2to + 4tm + tp4
- 34to + tm + tp6
- 4to + 4tm + tp6✓
सही उत्तर देखें
to + 4tm + tp6