Total Productive Maintenance (TPM) is being implemented in a bank's Data Centre to maximize the availability of its core banking systems. The TPM philosophy uses Overall Equipment Effectiveness (OEE) as a key performance indicator. If a server rack, which operates for 20 hours a day (Planned Production Time), experienced 1 hour of breakdown (Downtime) and ran at 90% of its optimal speed (Performance Rate), but only 80% of the transactions processed were error-free (Quality Rate), what is the effective Availability Rate component of the OEE calculation?
- 1The Availability Rate is 95%, calculated by multiplying the Performance Rate and the Quality Rate.
- 2The Availability Rate is 85%, calculated after adjusting for the quality losses.
- 3The Availability Rate is 90%, calculated by considering the speed factor after downtime.
- 4The Availability Rate is 95%, calculated based on the ratio of actual operating time to planned operating time.✓
Correct answer
The Availability Rate is 95%, calculated based on the ratio of actual operating time to planned operating time.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Industrial Engineering