Mathematics · Industrial Engineering
The expected time (te) of a PERT activity in project management is calculated using which formula? [where to = optimistic time, tm = most likely time, tp = pessimistic time]
- 1to + 4tp + tm6
- 2to + 4tm + tp4
- 34to + tm + tp6
- 4to + 4tm + tp6✓
Correct answer
to + 4tm + tp6