परियोजना नेटवर्क विश्लेषण में क्रांतिक पथ पद्धति (CPM) को किस रूप में वर्गीकृत किया गया है?
- 1घटना-उन्मुख (event oriented) नेटवर्क
- 2गतिविधि-उन्मुख (activity oriented) नेटवर्क✓
- 3शिथिलता-उन्मुख (slack oriented) नेटवर्क
- 4संभाव्यता-उन्मुख (probabilistic oriented) नेटवर्क
सही उत्तर देखें
गतिविधि-उन्मुख (activity oriented) नेटवर्क