Computer · PERT and CPM
नीचे दिए गए प्रोजेक्ट नेटवर्क डेटा के आधार पर, पहचानें कि कौन सी गतिविधि गैर-महत्वपूर्ण (non-critical) है: गतिविधिपूर्ववर्तीअवधिP--3Q--4RP4SP, Q3TR3UR, S4
- 1U
- 2T✓
- 3R
- 4P
सही उत्तर देखें
T