Computer · PERT and CPM
Based on the project network data given below, identify which activity is non-critical: ActivityPredecessorDurationP--3Q--4RP4SP, Q3TR3UR, S4
- 1U
- 2T✓
- 3R
- 4P
Correct answer
T
Download Single Question PDF