Computer · PERT and CPM
The time estimates obtained from four contractors P, Q, R, and S for executing a particular job are as under: ContractorOptimistic time (to)Most likely time (tm)Pessimistic time (tp)P51013Q6912R51014S41013 Which one of the contractors is more certain about completing the work in time?
- 1Contractor P
- 2Contractor Q✓
- 3Contractor R
- 4Contractor S
Correct answer
Contractor Q