क्रांतिक पथ (critical path) पर होने वाली गतिविधियों के लिए कुल फ्लोट (total float) का मान क्या होगा?
- 1कभी धनात्मक तो कभी ऋणात्मक
- 2शून्य✓
- 3ऋणात्मक
- 4धनात्मक
सही उत्तर देखें
शून्य