Computer · Construction Management
किसी गतिविधि (activity) को पूरा करने के लिए आवश्यक अनुमानित समय को क्या कहा जाता है?
- 1स्वतंत्र फ्लोट (Independent float)
- 2मुक्त फ्लोट (Free float)
- 3अवधि (Duration)✓
- 4फ्लोट (Float)
सही उत्तर देखें
अवधि (Duration)