Computer · Construction Management
एक PERT नेटवर्क के क्रांतिक पथ (critical path) पर 9 गतिविधियाँ हैं। यदि क्रांतिक पथ पर प्रत्येक गतिविधि का मानक विचलन 3 है, तो क्रांतिक पथ का मानक विचलन क्या है?
- 19✓
- 23√3
- 3√3
- 43
सही उत्तर देखें
9
Download Single Question PDF