Which of the following represents the longest sequence of dependent activities in a project network diagram that must be completed on time to ensure the project is finished within the minimum duration?
- 1Dummy Path
- 2Event
- 3Critical Path✓
- 4Non Critical Path
Correct answer
Critical Path