The critical path in a CPM network diagram is the path that connects the critical activities and is:
- 1sometimes the shortest path
- 2sometimes the longest path
- 3always the shortest path in terms of duration
- 4always the longest path in terms of duration✓
Correct answer
always the longest path in terms of duration