PERT गतिविधि के लिए निम्नलिखित में से कौन सा संबंध सही है? [जहाँ, te = अपेक्षित समय, to = आशावादी समय, tp = निराशावादी समय, tm = सबसे संभावित समय]
- 1tm = 6te − tp − 4to
- 2tm = 6te − tp − to4✓
- 3tm = 6te + to + tp4
- 4tm = 6te − to + tp4
सही उत्तर देखें
tm = 6te − tp − to4