In project management, what is the formula to calculate the 'expected time' (Te) of an activity? (where a = optimistic time, m = most likely time, b = pessimistic time)
- 1Te = a + 4m + 5b6
- 2Te = a + 4m + b8
- 3Te = a + 4m + b6✓
- 4Te = 2a + 4m + b6
Correct answer
Te = a + 4m + b6