In a network diagram, if activity 4-5 depends on activities 2-4 and 3-4, then activity 4-5 can be started only when:
- 1activity 2-3 is completed
- 2both activity 2-4 and 3-4 are completed✓
- 3activity 2-4 is completed
- 4activity 3-4 is completed
Correct answer
both activity 2-4 and 3-4 are completed