Mathematics · Industrial Engineering
During a week, a worker produced 300 units, working 48 hours, at an hourly rate of Rs. 4. The estimated standard time to produce a unit is 10 minutes. Calculate the total earnings of the worker under the Halsey premium plan.
- 1Rs. 196✓
- 2Rs. 216
- 3Rs. 200
- 4Rs. 190
Correct answer
Rs. 196