PERT विश्लेषण में, किसी भी गतिविधि को पूरा करने के लिए संभावित अपेक्षित समय (probabilistic expected time) की गणना निम्नलिखित में से किस समय अनुमान का उपयोग करके की जाती है?
- 1ये सभी✓
- 2सबसे संभावित समय (Most likely time)
- 3निराशावादी समय (Pessimistic time)
- 4आशावादी समय (Optimistic time)
सही उत्तर देखें
ये सभी