Computer · Construction Planning and Management
In PERT analysis, the probabilistic expected time for the completion of any activity is calculated using which of the following time estimates?
- 1All of these✓
- 2Most likely time
- 3Pessimistic time
- 4Optimistic time
Correct answer
All of these