Mathematics · Standard Costing and Variance Analysis
At 'Gati' Center, the standards for a handset are: 2 OLED screens at 4,000 each; 3 labor hours at 600 per hour. Variable overhead is 300 per labor hour. August output was 9,500 handsets. Purchased: 20,000 screens for 78,000,000. Used: 19,200 screens. Labor paid: 29,000 hours (includes 500 hours idle time) for 17,980,000. Based on this, calculate the Material Price Variance (on purchase), Material Usage Variance, and Labor Efficiency Variance.
- 1Material Price Variance: +2,000,000; Material Usage Variance: +800,000; Labor Efficiency Variance: -300,000
- 2Material Price Variance: +1,920,000; Material Usage Variance: -800,000; Labor Efficiency Variance: 0
- 3Material Price Variance: +2,000,000; Material Usage Variance: -800,000; Labor Efficiency Variance: 0✓
- 4Material Price Variance: +2,000,000; Material Usage Variance: -800,000; Labor Efficiency Variance: -300,000
Correct answer
Material Price Variance: +2,000,000; Material Usage Variance: -800,000; Labor Efficiency Variance: 0
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length Mathematics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Standard Costing and Variance Analysis?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Standard Costing and Variance Analysis