सामग्री आवश्यकता योजना (Material Requirements Planning - MRP) की प्राथमिक आउटपुट रिपोर्ट निम्नलिखित में से किसे माना जाता है?
- 1नियोजित ऑर्डर अनुसूची (Planned order schedule)✓
- 2नियोजन रिपोर्ट (Planning reports)
- 3प्रदर्शन नियंत्रण रिपोर्ट (Performance control reports)
- 4अपवाद रिपोर्ट (Exception reports)
सही उत्तर देखें
नियोजित ऑर्डर अनुसूची (Planned order schedule)