विस्तृत परियोजना रिपोर्ट (DPR) का कौन सा अनुभाग कार्य विखंडन संरचना (WBS) का उपयोग करके परियोजना की अनुसूची और चरणबद्धता प्रदान करता है?
- 1गुणवत्ता प्रबंधन योजना (Quality Management Plan)
- 2जोखिम मूल्यांकन (Risk Assessment)
- 3कार्यकारी सारांश (Executive Summary)
- 4परियोजना कार्यान्वयन अनुसूची (Project Implementation Schedule)✓
सही उत्तर देखें
परियोजना कार्यान्वयन अनुसूची (Project Implementation Schedule)