Computer · Construction Management
माप पुस्तिका (Measurement Book) में निम्नलिखित में से किसका रिकॉर्ड नहीं रखा जाता है?
- 1कार्य की मात्रा
- 2कार्य के आयाम (Dimensions)
- 3नकद अंतर्वाह और बहिर्वाह (Cash inflow and outflow)✓
- 4कार्य की दिशा
सही उत्तर देखें
नकद अंतर्वाह और बहिर्वाह (Cash inflow and outflow)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management