Computer · Estimation and Costing
प्रगति के दौरान किसी परियोजना के लिए आवश्यक अतिरिक्त कार्य के लिए निम्नलिखित में से कौन सा प्राकलन (estimate) लागू होता है?
- 1मात्रा प्राकलन (Quantity estimate)
- 2विस्तृत प्राकलन (Detailed estimate)
- 3पूरक प्राकलन (Supplementary estimate)✓
- 4संशोधित प्राकलन (Revised estimate)
सही उत्तर देखें
पूरक प्राकलन (Supplementary estimate)