परियोजना प्रबंधन में क्रिटिकल पाथ मेथड (CPM) मुख्य रूप से है:
- 1केवल संसाधन-प्रतिबंधित
- 2समय-स्वतंत्र
- 3इवेंट-उन्मुख (Event-oriented)
- 4गतिविधि-उन्मुख (Activity-oriented)✓
सही उत्तर देखें
गतिविधि-उन्मुख (Activity-oriented)