Computer · Construction Management
परियोजना प्रबंधन नेटवर्क (CPM) में, एक क्रांतिक गतिविधि (critical activity) में क्या होता है?
- 1शून्य कुल फ्लोट (Zero total float)✓
- 2स्वतंत्र फ्लोट (Independent float)
- 3न्यूनतम ऋणात्मक फ्लोट
- 4अधिकतम फ्लोट (Maximum float)
सही उत्तर देखें
शून्य कुल फ्लोट (Zero total float)
Download Single Question PDF