परियोजना प्रबंधन के नेटवर्क विश्लेषण में निम्नलिखित में से कौन सा विकल्प किसी भी समय या संसाधन की खपत नहीं करता है?
- 1समवर्ती संचालन (Concurrent operations)
- 2छद्म गतिविधि (Dummy activity)✓
- 3शिथिलता (Slack)
- 4गतिविधि (Activity)
सही उत्तर देखें
छद्म गतिविधि (Dummy activity)