परियोजना प्रबंधन की क्रांतिक पथ विधि (CPM) के लिए आवश्यक है:
- 1चौगुना समय अनुमान (Four time estimate)
- 2तिहरा समय अनुमान (Triple time estimate)
- 3दोहरा समय अनुमान (Double time estimate)
- 4एकल समय अनुमान (Single time estimate)✓
सही उत्तर देखें
एकल समय अनुमान (Single time estimate)