परियोजना प्रबंधन (project management) में, कार्य विभाजन संरचना (Work Breakdown Structure - WBS) का उपयोग करते समय कौन सा संरचनात्मक योजना दृष्टिकोण अपनाया जाता है?
- 1विकेंद्रीकृत दृष्टिकोण (Decentralized approach)
- 2टॉप-डाउन दृष्टिकोण (Top-down approach)✓
- 3क्षैतिज दृष्टिकोण (Horizontal approach)
- 4बॉटम-अप दृष्टिकोण (Bottom-up approach)
सही उत्तर देखें
टॉप-डाउन दृष्टिकोण (Top-down approach)