परियोजना नेटवर्क क्रैशिंग (network crashing) के दौरान, न्यूनतम _____ वाली गतिविधि को सबसे पहले क्रैश किया जाना चाहिए।
Verified Solution4 OptionsUpdated: October 2026👁️1 View
Share:
- 1सामान्य समय (Normal time)
- 2क्रैश लागत (Crash cost)
- 3सामान्य लागत (Normal cost)
- 4लागत ढाल (Cost slope)✓
सही उत्तर देखें
लागत ढाल (Cost slope)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
👥
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Online Test Series
Preparing for Physics?
Practice full-length Physics mock tests with real exam timers, instant score analysis, and all-India ranking.
Chapter Practice
Practice Project Management Techniques MCQs →Want more practice questions on Project Management Techniques?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Project Management Techniques