Computer · Construction Management
नेटवर्क योजना में किसी गतिविधि का प्रारंभिक समाप्ति समय (EF), उसके प्रारंभिक प्रारंभ समय (ES) और उसकी अवधि (t) का ________ होता है।
- 1अनुपात (Ratio)
- 2गुणनफल (Product)
- 3अंतर (Difference)
- 4योग (Sum)✓
सही उत्तर देखें
योग (Sum)