Physics · Construction Planning and Management
निम्नलिखित परियोजना प्रबंधन तकनीकों में से कौन सी गतिविधि-उन्मुख (activity-oriented) है?
- 1PERT और CPM दोनों
- 2CPM✓
- 3गैंट चार्ट (Gantt Chart)
- 4PERT
सही उत्तर देखें
CPM