General Studies · Project Management Techniques
निम्नलिखित को छोड़कर सभी समय-इवेंट नेटवर्क विश्लेषण (time-event network analysis) की प्रमुख तकनीकें हैं:
- 1गैंट चार्ट (Gantt chart)
- 2कार्यक्रम मूल्यांकन और समीक्षा तकनीक (PERT)
- 3क्रांतिक पथ विधि (Critical path method)
- 4रैखिक प्रोग्रामिंग (Linear programming)✓
सही उत्तर देखें
रैखिक प्रोग्रामिंग (Linear programming)