Computer · Construction Management
क्रिटिकल पाथ मेथड (CPM) एक _______ ओरिएंटेड तकनीक है, जिसका उपयोग परियोजना प्रबंधन में किया जाता है।
- 1संसाधन (resource)
- 2घटना (event)
- 3समय (time)
- 4गतिविधि (activity)✓
सही उत्तर देखें
गतिविधि (activity)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management