औद्योगिक इंजीनियरिंग अनुप्रयोगों में, PERT कितने समय अनुमानों का उपयोग करता है?
- 1एक समय अनुमान
- 2तीन समय अनुमान✓
- 3चार समय अनुमान
- 4दो समय अनुमान
सही उत्तर देखें
तीन समय अनुमान